嗨,我们获得了100个简单的PC报告的副本(其中一个内置的报告中的一个克隆)。似乎在星期天时间发生变化毕竟报告的时间表似乎触发了比他们应该的一小时。所以他们随后跑过一直跑到实际触发的时候。
例如:
每日报告安排早上7点,直到早上7点凌晨6点(超过718倍),直到早上7点(它超过一点,例如,我假设的是它只是追赶que)。
我已删除报告,创建了全新的,设置新的时间表,检查PC CVM上的时间(正确)。试图重新启动服务/群集停止/重启等。甚至尝试将PC更新为2021.1.0.1(修复了我们拥有的PDF报告问题,但不是这一件)。
还有谁有相同的问题吗?
最好的答案Alona
I found some internal information on this and you have done everything right and beyond it. You have re-created the schedule and even the report. I\u2019ll include the steps below just in case. But if you think you have done all that and it still doesn\u2019t work could you please open a case with Nutanix Support?<\/p>
Remove the schedule<\/span><\/p> Edit the report.<\/span><\/p>\t<\/li>\t In the upper left corner click \u2018Edit Schedule\u2019.\u00a0<\/span><\/p>\t<\/li>\t At the bottom of the popup click the option to remove the schedule.<\/span><\/p>\t<\/li>\t Save the Report Config. This will stop the report generation from continuing.<\/span><\/p>\t<\/li><\/ol> \u00a0<\/p> Set up a Schedule with Playbooks<\/span><\/p> Go to Operations > Playbooks from the hamburger menu.<\/span><\/p>\t<\/li>\t Select Create Playbook.<\/span><\/p>\t<\/li>\t You must first set a trigger - in this case, set a Time Trigger.<\/span><\/p>\t<\/li>\t From the time trigger customization screen - change the radio button to configure a schedule at a recurring interval.<\/span><\/p>\t<\/li>\t Fill in the rest of the details to match the desired schedule frequency.<\/span><\/p>\t<\/li>\t Now you need to add the actions. Click Add action on the left-hand side.<\/span><\/p>\t<\/li>\t Search for Generate Report and click the Select button to add the Generate report action<\/span><\/p>\t<\/li>\t Choose the report config you would like to configure the schedule for and fill out any of the details you would like for how this report is generated.<\/span><\/p>\t<\/li>\t Now add one more action and search for the Email action.<\/span><\/p>\t<\/li>\t Fill in the details of the email action and be sure to add the report into the attachment field (click the dropdown and you should see the option to add it).<\/span><\/p>\t<\/li>\t Hit save and close. Be sure to click the enabled toggle to enable the Playbook.<\/span><\/p>\t<\/li><\/ol>